Saturday, 1 May 2010

Paper prototyping risk management case study

The day-by-day experiences of a usability team working with a software development team. The article covers their activities over 6 days, as the development team got to see first hand how end users found their software, and what they needed to change.

By using paper prototyping and usability testing, the development team managed their risks by focusing on them earlier in the project, while there was still time to make changes. We had started the process by having the team pick those areas which they had perceived as most critical to the success of the next release - the areas of highest risk.

Using paper prototypes to manage risk - article by Carolyn Snyder for uie.com

No comments:

Post a Comment